The announcement of the first floating WTG installation for Arcadis Ost 1 followed by the signing of a conditional agreement for turbine supply between Parkwind and MHI Vestas marked the first day of the Wind Europe conference in Copenhagen.

Parkwind’s German Arcadis Ost 1 project will be the first offshore wind farm that will make use of a floating vessel for the installation of Wind Turbine Generators. This achievement is the result of a year-long joint development between Parkwind, Heerema Marine Contractors and MHI Vestas Offshore Wind.

After being a successful bidder in the German offshore wind auction in 2018, Parkwind is developing the 257 MW Arcadis Ost 1 offshore windfarm. The project, located 20 km northeast of the island of Rugen in the Baltic Sea, will consist of 27 MHI Vestas V174-9.5MW turbines mounted on monopile foundations and one offshore substation. The Arcadis Ost 1 windfarm will supply green power to an estimated 300,000 German households.

Considering the challenging soil conditions at the Arcadis Ost 1 site, Parkwind looked at possible alternatives to traditional installation methodologies. In joint cooperation with Heerema Marine Contractors and MHI Vestas, the floating installation method was developed.

This innovative installation methodology provides two unique advantages;
it avoids all interaction with the soil thereby reducing the project’s risk compared to a traditional jack up installation and this method allows for a reduced installation time. The floating installation method contributes to the further reduction of the levelized cost of offshore wind energy and will unlock the potential of many offshore areas around the world.

The developed method is based on utilizing a floating installation vessel to assemble the WTG components. The vessel will have all turbine components on its deck including a dummy tower. This tower will provide a stable platform on board the vessel to assemble the nacelle and the blades. The first step will be lifting the WTG tower onto the pre-installed turbine foundation. The second step is the most advanced element in the assembly process which includes lifting the nacelle onto the dummy tower and attaching the blades.
This process ensures full control over the blades thereby guaranteeing a safe and highly reliable blade assembly. After the Rotor Nacelle Assembly [RNA] on the installation vessel, the complete RNA will be lifted as one piece onto the WTG tower.

“Taking the turbine installation based on a floating vessel from theory to practice is a major step forward for the offshore wind industry,” commented Parkwind’s co-CEO Eric Antoons, “supported by Heerema Marine Contractors and MHI Vestas, we saw this as the best solution for our German Arcadis Ost 1 project where soil conditions are challenging.”

Koos-Jan van Brouwershaven, CEO of Heerema Marine Contractors, added: “More than one year ago, Heerema Marine Contractors, together with our partners MHI Vestas and Parkwind, started an intensive research to find out the possibilities of installing turbines utilizing our fleet of floating assets. In our Simulation Center, we created an authentic visualization of the local situation, including crane and vessel controls, realistic weather conditions, sea swell patterns and seabed conditions. This collaboration led to an innovative method which will be used for the installation of turbines in the Arcadis Ost 1 wind park. Heerema Marine Contractors is very proud to participate in this unique project. It shows our ambition to remain a frontrunner in the offshore energy market, and our commitment to operate in wind projects all over the world.”

Furthermore, Arcadis Ost 1 will be the first offshore wind farm to install the newly developed MHI Vestas V174 turbines.

“We are exceptionally pleased to be chosen by Parkwind once again for such a milestone project,” said Henrik Jensen, MHI Vestas Chief Sales Officer. “Today’s announcement is a testament to the strong partnership and trust between Parkwind and MHI Vestas as we embark on our fifth project together. We look forward to bringing our technology and experience to bear at Arcadis Ost 1 and contributing to the German renewable energy transition.”

CLOSE

Maarten van der Horst

Head of Projects

Maarten joined Parkwind and more specifically the Oriel project team in early 2021. He brings 17 years of experience in the energy industry having worked at Engie's renewables arm first as an engineer, later as offshore specialist.

CLOSE

Wim Verrept

IT Services Manager

He joined Parkwind in 2016 as risk manager, during the installation phase of Nobelwind. Since then his responsibilities have expanded to include IT and the QHSSE department. Before joining the company, he worked as a risk manager at large financial institution in Belgium.

CLOSE

Ingrid Dony

HR Manager

Ingrid joined Parkwind in 2013 and manages the Human Resources department. Her expertise in corporate HR has created the foundations in Parkwind’s evolving and rapidly growing employee and consultant base. Her team manages everything from payroll to employee development and communications. She has been instrumental in preparing the organization for international expansion and the digitalization of numerous HR legal and administrative tools.

CLOSE

Dirk Dewettinck

Head of R&D

At Parkwind since 2015 he manages the engineering resources involved in project development, design and construction. He was closely involved in the technical management of the Nobelwind and Northwester 2 projects. Prior to joining Parkwind, he was involved in other offshore wind projects, working for a major wind turbine supplier, and prior to that he worked for more than 15 years with major engineering contractors in projects around the world, mainly in the conventional power generation construction and services (steam, gas, nuclear).

CLOSE

Clément Helbig de Balzac

Project Director Arcadis Ost 1

Joining Parkwind in 2011 as a project finance specialist and he was heavily involved in the financing and construction of Northwind and Nobelwind. Thereafter, as project finance manager, he led the financing process of Northwester 2 and the refinancing of three operational offshore wind farms of the Parkwind portfolio. He is also involved in business development projects for his expertise lies in financing processes, construction contract negotiation, contracting strategy and development and construction management.

CLOSE

Edward Van Melkebeek

Head of Technology

Since joining Parkwind in 2018, he has been leading the Technology team responsible for leveraging Parkwind’s know-how in civil, electrical and WTG packages to development of new projects. The team also performs a supply chain role, managing technical aspects of project contracts. Previously, he has built extensive practical and managerial experience in the offshore construction business for over 22 years at a global leading dredging and offshore contractor strongly active in the offshore wind industry.

CLOSE

Mathias Van Steenwinkel

Business Development Manager

He joined Parkwind in 2012 working on financial modelling, PPA negotiations and the overall financial close processes. Since 2016, he is heading the growing business development department playing a key role in the identification of new projects, global partnerships and tender preparations.

CLOSE

Kristof Verlinden

O&M Manager

With Parkwind since 2010, he is responsible for the asset management and production management of all of Parkwind’s offshore operational assets. The O&M organization plays a pivotal role in project development incorporating strategic insight to ensure frictionless O&M operations from the moment of first production. The team also supplies external support services, is involved in numerous R&D initiatives with universities and wind farm performance analysis using state of the art data systems. Kristof joined Parkwind with an engineering background in international service support business and wind turbine driveline design validation.

CLOSE

Pieter Marinus

General Counsel and Investment Relations Director

As a former Parkwind board member, he has been involved in the financial close and follow-up of every Parkwind project as well as in their acquisition and divestment processes. Prior to joining Parkwind’s management in 2017, he was also in charge of multiple other renewable energy investments and financings around Europe, notably as Investment Director at Korys.

CLOSE

Peter Caluwaerts

Head of Engagement Management

After years of building extensive experience in large construction works, he started his career in offshore wind in 2010 by taking up the role of CLO of Parkwind, responsible for regulatory, legal and contracting matters for Belwind and Northwind windfarms. Since then, as Project Director, he’s led the Northwester 2 project completed in 2020 and is now responsible for Parkwind’s Irish projects Oriel and Clogherhead. He plays an instrumental role in organizing Parkwind’s international expansion and growth.

CLOSE

Eric Antoons

co-CEO

Before joining the company in 2013, he worked for one of the largest power and gas suppliers in Belgium, in both operational and executive functions. Joining Parkwind in 2013 as COO, he supervised the construction of three wind farm projects and the considerable growth of O&M activities. Since becoming co-CEO in 2016, he has also developed Parkwind’s R&D activities to the forefront partnering with universities and several technology start-ups.

CLOSE

François Van Leeuw

co-CEO

He joined Parkwind as CFO in 2009 and has been leading the financing and development of Parkwind's first wind farms. In his role he’s particularly involved in new business and partnership development for Parkwind globally. He is also serving as the chairman of the Belgian Offshore Platform, the non-profit association of investors and owners of Belgian wind farms.

CLOSE

Paul Tummers

CFO

Arriving to Parkwind in 2019, after a broad career in energy and infrastructure, he has taken a leading role in Parkwind’s international expansion from both corporate finance and organizational restructuring.